Work Center in SAP PP: Create, Change, Display

 Work center is an organization unit where manufacturing activities are performed.

In other words, Work Centers are the master data which represent real machines, Production Lines, Assembly Work Center, etc. Manufacturing activity or Operations are carried out at Work Center.

  • Work Centers are used in task list (routing) operations and is copied to production orders or process orders for the shop floor planning and execution.
  • Work Center data is used for

  1. Scheduling

    When a production order is created, the duration of an operation can be calculated based on operating times in routing and formulas which are entered in the Work Center.

  2. Costing

    The costs of an operation can be calculated in the production Order based on the formulas which are entered in the Work Center. Work Center is also linked to a cost center.

  3. Capacity Planning

    The available capacity and formulas for calculating capacity requirements are stored in the Work Center.

  • Work Centers are used in routing operation data.
  • Work Center is created for a manufacturing plant and is identified by a code.
  • Group of similar machines can also be created as a single Work Center. For example, 5 similar machines can be created as 1 Work Center with a number of capacities as 5.

How to create Work Center

Step 1) From SAP Easy access open transaction CR01

  1. Enter your manufacturing Plant code where Work Center needs to be created.
  1. Enter Work Center code.
  1. Enter the Work Center category as “0001” which means Work Center would be categorized as machines.

Work Center in SAP PP: Create, Change, Display


After filling in all the fields, click Work Center in SAP PP: Create, Change, Display or press Enter to go to the next screen.


Step 2) In this Screen, Work Center basic data would be entered as given below.

  1. Input Work Center description.
  1. Enter person responsible code for that Work Center.
  1. Enter physical location where Work Center is located in the plant.
  1. Enter usage as “009” which means Work Center is valid for all task list types such as production routing, maintenance task list, etc.
  1. Enter standard Value key which contains different activity types used for standard cost calculation.

Work Center in SAP PP: Create, Change, Display


Step 3) In this Screen under “Capacities Tab.”

  1. Enter Capacity category as “001” which represents machine category.
  1. Input processing formula as “SAP006” – It is used to calculate the available capacity of Work Center.

SAP006 =( Operation quantity* machine time )/ base quantity

  1. After filling in the capacity category and processing formula, click on the Work Center in SAP PP: Create, Change, Display button:

Work Center in SAP PP: Create, Change, Display


It will open another screen.


Step 4) In this Screen under capacities Tab, capacity data will be entered.

  1. Enter Capacity description.
  1. Enter details about “Input capacity planner group”, which is responsible for machine capacity.
  1. Enter factory calendar ID, which has public holidays listed for your plant. So, on holidays, capacity for that Work Center would be zero.
  1. Input base unit of measure as “MIN” which means work center available capacity will be measured in time i.e. min.
  1. Enter the time period (start and finish time) for which Work Center would be available for operation.
  1. Enter capacity utilization percentage %( how much time it is utilized out of the standard available working time) of the Work Center considering the breakdown and preventive maintenance of the machine. Input number of capacities which means a number of similar Work Center.
  1. Check “relevant for finite scheduling and “long term planning” flags which indicate if there is a capacity constraint, then the operation is moved to a certain date where it can be processed without capacity constraints.

Work Center in SAP PP: Create, Change, Display


After filling in all the fields, clickWork Center in SAP PP: Create, Change, Display to go back to the Work Center capacity overview.

Then click on the tab “Scheduling” tab from the menu, the system will show the following screen:


Step 5) In Scheduling Tab,

  1. Enter Capacity category as “001” which represents machine category and hence machine time would be the basis for calculating schedule time in production order.
  2. Input processing formula as “SAP002” which is used to calculate scheduling time.

SAP002 = (Operation quantity* machine time)/ base quantity/no. of splits.


Work Center in SAP PP: Create, Change, Display


After filling in all the fields, click on the tab “Costing.”


Step 6) In Costing Tab

  1. Enter Start and Finish date which represents validity date of the cost center.
  2. Input cost center to which operational costs would be booked.
  3. Input all activity types along with the formulae, which would be used for calculating the activity costs.

Work Center in SAP PP: Create, Change, Display


Click button Work Center in SAP PP: Create, Change, Display to save the new Work Center. The system will show message Work Center in SAP PP: Create, Change, Displayat the lower left corner.


How to Change Work Center

We require changes in Work Center if the cost center assigned to the work center has been changed by the finance team. If Work Center available time for production or its utilization % has been changed, then also we need to make changes in the work center.


Step 1) From SAP Easy access screen, open the transaction CR02.

  1. Enter Plant Code.
  2. Enter Work Center code which needs to be changed.

Work Center in SAP PP: Create, Change, Display


After filling in all the fields, click Work Center in SAP PP: Create, Change, Display to go to the overview screen of the Work Center. You can also directly go to the preferred tab by using the Work Center in SAP PP: Create, Change, Display buttons.


Step 2)

  1. Change the Cost Center or do any kind of modifications like a change of available time or utilization % in any of the tabs.

Work Center in SAP PP: Create, Change, Display


After finishing all modifications, click Work Center in SAP PP: Create, Change, Display to save Work Center. The system will show a message like Work Center in SAP PP: Create, Change, Displayat the lower left corner.


How to display Work Center

Step 1) From SAP Easy Access screen open the transaction CR03

  1. Enter Plant Code.
  2. Enter Work Center code which needs to be displayed.

Work Center in SAP PP: Create, Change, Display


After filling in all the fields, press enter from the keyboard to go to the overview screen of the Work Center. You can also directly go to the preferred tab by using the Work Center in SAP PP: Create, Change, Display buttons.


Troubleshooting


  • There might be the case where in Cost Center does not exist. For this, you need to create the cost center and maintain activity type – cost center relationships.
  • If you go to the technology tab you will get stuck on selecting a machine type, if so click Work Center in SAP PP: Create, Change, Display to leave the tab.
  • Person responsible, capacity planner groups needs to be configured in order to proceed with Work Center creation.

Comments

Popular posts from this blog

How to Create Production version in SAP PP C223

  The production version is the link between a product BOM (Bill of Material) and the process Routing. It determines which alternative BOM is used together with which routing to produce a material or plan a material. There may be different production versions based on the lot sizes and validity dates. For example, there may be different versions if you want to produce 1 – 100 liter of paint than 100 – 1000 liter of paint, as such the different composition of BOM may be required in both cases. It comprises of the following data: The assignment of routings to the production version The assignment of the alternative BOM to the production version Production versions are used in material requirements planning (MRP), production order creation, and product costing to select the most suitable routing and the corresponding bill of material. In order to create production version, perform the following steps- Step 1)  From SAP Easy access screen open transaction  C223 Enter Plant Code. Enter pare

Introduction to SAP PP (Production Planning)

  What is Production Planning? Production Planning is the process of aligning demand with manufacturing capacity to create production and procurement schedules for finished products and component materials. SAP PP is an important module of SAP. It tracks and makes a record of the manufacturing process flows, for example, the planned and actual costs. Also, goods movements from the conversion of raw material to semi-finished goods. It is fully integrated with the other SAP modules: SD, MM, QM, FICO & PM. Organization Structure in SAP PP In any live Production Planning module, locations of manufacturing plants and storage within the plants, should be available in the system. Importance of Plant and storage locations in Production Planning- All Production master data is created at Plant level. Planning activities are also performed at Plant level. Production Confirmation process and related goods movement occur at plant and storage location level. Master Data in SAP PP Master data is

Production Order in SAP: CO01, MD16, CO02, CO15

  A production order defines which material is to be processed, at which location, and at what time and how much quantity is required. It also defines which components and sequence of operations are to be used and how the order costs are to be settled. Planned orders are results of running MRP. Shortages of materials that are set to internal procurement will create planned orders, which can be converted into production orders. Production orders are “hard copies”; they cannot be adjusted by an MRP run anymore. BOM and routing data of the materials are copied into the production order which determines the list of components and operational data in the order. Planned Costs also gets updated in the production order via component price and routing activity price. You can run an availability check on production orders which determines any missing components in the order so that you can bring that missing component for the order execution at shop floor. You can print the production order for

What is SAP? Meaning of SAP ERP Software

  What is SAP? SAP  stands for Systems Applications and Products in Data Processing. SAP, by definition, is also the name of the ERP (Enterprise Resource Planning) software as well as the name of the company. SAP Software is a European multinational, founded in 1972 by Wellenreuther, Hopp, Hector, Plattner, and Tschira. They develop software solutions for managing business operations and customer relationships. SAP system consists of a number of fully integrated modules, which covers virtually every aspect of business management. SAP is #1 in the ERP market. As of 2010, SAP has more than 140,000 installations worldwide, over 25 industry-specific business solutions and more than 75,000 customers in 120 countries. Other Competitive products of SAP Software in the market are Oracle, Microsoft Dynamics, etc. What is SAP ERP? Why is it Required? The very fundamental question for any beginners is why Enterprise Resource Planning also called ERP, is required? To answer this, let’s examine thi

SAP PP Reports Tutorial: COOIS, MB52, CS15, CS12

  There are many reports available in SAP pertaining to Master Data, Production Orders and Goods Movement against orders. It helps users to view the overall situation of the plant with ease Through PP reports, you can view Production and Consumption data about the material for the specific time period. Current Plant stock can also be displayed real time You can also see target order quantity to be executed and track the orders through various order status via standard SAP reports How to display order information systems This order info system displays the list of orders along with the quantity, dates, and their status. You can also see the goods movement on the orders. This gives view for the shop floor person to plan and execute the orders which are on priority, and you can see the actual delivered quantity against the plan. Step 1)  From SAP Easy access screen open transaction COOIS Select the option “Order Headers” in the List field Flag production orders checkbox Enter your manufac

Long Term Planning (LTP) in SAP PP: MS31, MS04, MD61

  SAP PP Long Term Planning (LTP) Long Term Planning (LTP) in SAP PP is used to simulate the future demand and supply situation in all BOM levels. The main function is to check the capacity situation, material requirement and vendor ability to provide the material in desired time. This is not an actual run but a simulative run where actual planning situation is not being affected, and we can see the capacity situation of the work centers well ahead in time. If such information is available in advance, then we can decide at an early date whether additional machines will be required to cope with capacity bottlenecks. LTP (Long Term Planning) is nothing but MRP run in simulation version to simulate the production plan for the future. It is possible to transfer the plan from simulative version to operative version “00”(actual planning) if through simulation it is found that all capacity and requirement can be fulfilled. The purchasing department can also utilize the outcome of long-term pl

SAP PP Capacity Planning: CM01, CM21

  The main function of capacity planning is to check the load at Work Center and do the capacity leveling i.e. balance the load at Work Center. It helps to calculate the production capacity based on the requirement of the product against the available capacity of the work center. MRP works with infinite capacity and creates planned orders at the Work Center at the same time since it assumes that Work Center is available all the time. So, it creates planned orders on the same date based on the requirements despite capacity shortages. You can execute those orders on that Work Center in the system which is not practically feasible in the shop floor. The main objective of the capacity leveling includes leveling overloads at Work Center and to achieve optimum utilization of Work Centers. MRP generated planned orders are converted to production orders which determine which Work Center is to be used, and accordingly the capacity requirements are generated on that Work Center. Capacity levelin