SAP PP Reports Tutorial: COOIS, MB52, CS15, CS12

 There are many reports available in SAP pertaining to Master Data, Production Orders and Goods Movement against orders.

  • It helps users to view the overall situation of the plant with ease
  • Through PP reports, you can view Production and Consumption data about the material for the specific time period. Current Plant stock can also be displayed real time
  • You can also see target order quantity to be executed and track the orders through various order status via standard SAP reports

How to display order information systems

This order info system displays the list of orders along with the quantity, dates, and their status. You can also see the goods movement on the orders.

This gives view for the shop floor person to plan and execute the orders which are on priority, and you can see the actual delivered quantity against the plan.

Step 1) From SAP Easy access screen open transaction COOIS

  1. Select the option “Order Headers” in the List field
  1. Flag production orders checkbox
  1. Enter your manufacturing plant code.
  1. Enter your Order type for which you want to fetch the Production Orders.If you don’t enter any order type, the report will show the data for all orders type for the plant.

SAP PP Reports Tutorial: COOIS, MB52, CS15, CS12


After filling in all the fields, click execute button on top or press F8 from keyboard to go to the next screen.


Step 2) In this Screen, you are going to see the list of Orders.

  1. List of orders with material code and target quantity are displayed.
  1. Order basic start and finish dates are displayed for the planner.
  1. Order status are shown by which you can identify whether the order is delivered or yet to be executed at shop floor.

SAP PP Reports Tutorial: COOIS, MB52, CS15, CS12


Press back button in order to exit from the report.

Step 3)In the Initial screen of Production Order information system( COOIS), you can also view the goods movement which has occurred against that order.

  1. Select “Documented goods movement ” from the List field
  1. Check flag of “Production Orders “
  1. Enter your production plant code
  1. Enter your Production Order type for which you want to display the documented goods movement. If you don’t enter any order type, the report will show the data for all orders type for the plant.

SAP PP Reports Tutorial: COOIS, MB52, CS15, CS12


Click execute button from the top or press F8 from the keyboard to run the report.

When you run the report, it will open another screen where goods movement are displayed.


Step 4)In this screen, documented goods movement against order are displayed.

  1. List of Orders along with parent material and its component material are displayed.
  1. You can see the movement type 261 and 101 which occurred against the order along with the batch number.

SAP PP Reports Tutorial: COOIS, MB52, CS15, CS12


Press back button in order to exit from the report.

How to display material document list

Material Document is generated whenever you do any kind of goods movement such as goods receipt, goods issue against production order, etc.

We can view the list of the material document which specifies the production and consumption of data for a plant.

Step 1) From SAP easy access screen, open transaction MB51.

  1. Enter your manufacturing plant code.
  1. Input the movement type 101 if you want to see Production data (Goods Receipt) for all materials.
  1. Enter the posting periods for which you want to display the production.

SAP PP Reports Tutorial: COOIS, MB52, CS15, CS12


Press execute button on top or press f8 from the keyboard to move to the next screen.


Step 2)In this screen, you will see the production data of all materials.

  1. List of material codes along with movement type 101 displayed.
  1. Movement quantity is displayed along with the posting date.

SAP PP Reports Tutorial: COOIS, MB52, CS15, CS12


Press F3 from the keyboard to exit the report.Now, we go back to SAP easy access screen to run other transaction.


Step 3) From SAP easy access screen, open transaction MB51.

  1. Enter your manufacturing plant code.
  1. Input the movement type 261 to see consumption data (Goods issue) for all the materials.
  1. Enter the posting periods for which you want to display the consumption.

SAP PP Reports Tutorial: COOIS, MB52, CS15, CS12


Press execute button on top or press f8 from the keyboard to move to next screen.

Step 2) In this screen, you will see the consumption data for all materials.

  1. List of material codes along with movement type 261 is displayed.
  2. Movement quantity is displayed along with the posting date.

SAP PP Reports Tutorial: COOIS, MB52, CS15, CS12


Press F3 from the keyboard to exit the report.

How to display Stock of multiple materials

After all goods movement are done, it updates the stock of the materials.Real time stock is available in this report for multiple materials at a single shot.

Step 1) From SAP easy access screen, open transaction MB52.

  1. Input single material code or range of material codes or keep it blank to pull the report for all materials.
  1. Enter your manufacturing plant code.
  1. Input storage location code or keep it blank to pull the report at plant level for all storage locations.

SAP PP Reports Tutorial: COOIS, MB52, CS15, CS12


Press execute button from top or press F8 from the keyboard to move to next screen. 

Step 2) In this screen, you will see the stock of all materials.

  1. List of material codes along with stock quantity and value at the storage location is displayed.

SAP PP Reports Tutorial: COOIS, MB52, CS15, CS12


Press F3 from the keyboard to exit the report.


How to display “where-used list” in BOM

This report is used to find out whether a component exists in the BOM’s. With this report, you can find out the parent material in which a component is used as BOM item.

It is basically reverse BOM explosion which means through component child code, you can find out the parent material code. For example Component like Tread is used as an item in BOM of Tyres.


Step 1) From SAP easy access screen, open transaction CS15.

  1. Input single material code for which you want to see the parent material.
  1. Flag “Direct” check box.
  1. Flag “Material BOM” as you are looking the component up in material BOM.
  1. Press Next button to move to next screen.

SAP PP Reports Tutorial: COOIS, MB52, CS15, CS12


Step 2) In this screen,

  1. Enter required quantity as “1”.
  1. Input your manufacturing plant.
  1. Flag “Multi-level” which means you want to see all upper BOM levels for the component.

SAP PP Reports Tutorial: COOIS, MB52, CS15, CS12


Press execute button on top or press F8 from the keyboard to move to next screen.

Step 3)In this screen,

  1. You can see the different levels of BOM in which this component exists
  1. You can see the parent material in which the component exists.

SAP PP Reports Tutorial: COOIS, MB52, CS15, CS12


Press F3 from the keyboard to exit the report.


How to display summarized multi level BOM

This report is used to explode multi-level BOM for the product. With this report, you can see all the components at all BOM levels in a single screen.

Step 1) From SAP easy access screen, open transaction CS12.

  1. Input single material code for which you want to see the list of components at all levels of BOM.
  1. Input your manufacturing plant code
  1. Input BOM application “PP01” which means you are going to explode production BOM.

SAP PP Reports Tutorial: COOIS, MB52, CS15, CS12


Press execute button from top or press F8 from the keyboard to move to next screen.

Step 2) In this screen,

  1. You will see the list of components along with quantity at all BOM explosion levels.

SAP PP Reports Tutorial: COOIS, MB52, CS15, CS12


Press F3 from the keyboard to exit the report.


Troubleshooting

  • If you are unable to execute any report, ensure your selection criterions are correct, and there are transactions data in the system for which you want to display reports.
  • For BOM reports, ensure material master is in place and BOMs already exists in the system then only you will be able to display such kinds of reports in SAP.
  • Ensure that you are aware of movement types before looking at any production or consumption reports in SAP.

Comments

Popular posts from this blog

How to Create Production version in SAP PP C223

  The production version is the link between a product BOM (Bill of Material) and the process Routing. It determines which alternative BOM is used together with which routing to produce a material or plan a material. There may be different production versions based on the lot sizes and validity dates. For example, there may be different versions if you want to produce 1 – 100 liter of paint than 100 – 1000 liter of paint, as such the different composition of BOM may be required in both cases. It comprises of the following data: The assignment of routings to the production version The assignment of the alternative BOM to the production version Production versions are used in material requirements planning (MRP), production order creation, and product costing to select the most suitable routing and the corresponding bill of material. In order to create production version, perform the following steps- Step 1)  From SAP Easy access screen open transaction  C223 Enter Plant Code. Enter pare

Bill of Material (BoM) in SAP PP: Create, Change, Display

  What is Bill of Material (BOM) and its role? A bill of material is a complete, formally structured list of the components that make up a product or assembly. The list comprises of the material number of each component, together with the quantity and unit of measure. BOM can be single level and multi-level. For example, finished material would contain semi-finished materials as components which in turn would contain raw materials as components in next level. There can be different alternative BOMs for a product depending upon the lot sizes, validity dates, and different production methods. BOM is used in production planning for semi-finished and purchase planning for raw materials. BOM’s are also used in standard cost calculation for finished Product by rolling up the cost from raw to semi-finish and then to finished Product. Material BOM can be made for material in PP module and equipment BOM are used in Plant Maintenance module. How to create BOM Step 1)  From SAP Easy access screen

Production Order in SAP: CO01, MD16, CO02, CO15

  A production order defines which material is to be processed, at which location, and at what time and how much quantity is required. It also defines which components and sequence of operations are to be used and how the order costs are to be settled. Planned orders are results of running MRP. Shortages of materials that are set to internal procurement will create planned orders, which can be converted into production orders. Production orders are “hard copies”; they cannot be adjusted by an MRP run anymore. BOM and routing data of the materials are copied into the production order which determines the list of components and operational data in the order. Planned Costs also gets updated in the production order via component price and routing activity price. You can run an availability check on production orders which determines any missing components in the order so that you can bring that missing component for the order execution at shop floor. You can print the production order for

Introduction to SAP PP (Production Planning)

  What is Production Planning? Production Planning is the process of aligning demand with manufacturing capacity to create production and procurement schedules for finished products and component materials. SAP PP is an important module of SAP. It tracks and makes a record of the manufacturing process flows, for example, the planned and actual costs. Also, goods movements from the conversion of raw material to semi-finished goods. It is fully integrated with the other SAP modules: SD, MM, QM, FICO & PM. Organization Structure in SAP PP In any live Production Planning module, locations of manufacturing plants and storage within the plants, should be available in the system. Importance of Plant and storage locations in Production Planning- All Production master data is created at Plant level. Planning activities are also performed at Plant level. Production Confirmation process and related goods movement occur at plant and storage location level. Master Data in SAP PP Master data is

What is SAP? Meaning of SAP ERP Software

  What is SAP? SAP  stands for Systems Applications and Products in Data Processing. SAP, by definition, is also the name of the ERP (Enterprise Resource Planning) software as well as the name of the company. SAP Software is a European multinational, founded in 1972 by Wellenreuther, Hopp, Hector, Plattner, and Tschira. They develop software solutions for managing business operations and customer relationships. SAP system consists of a number of fully integrated modules, which covers virtually every aspect of business management. SAP is #1 in the ERP market. As of 2010, SAP has more than 140,000 installations worldwide, over 25 industry-specific business solutions and more than 75,000 customers in 120 countries. Other Competitive products of SAP Software in the market are Oracle, Microsoft Dynamics, etc. What is SAP ERP? Why is it Required? The very fundamental question for any beginners is why Enterprise Resource Planning also called ERP, is required? To answer this, let’s examine thi

SAP PP Capacity Planning: CM01, CM21

  The main function of capacity planning is to check the load at Work Center and do the capacity leveling i.e. balance the load at Work Center. It helps to calculate the production capacity based on the requirement of the product against the available capacity of the work center. MRP works with infinite capacity and creates planned orders at the Work Center at the same time since it assumes that Work Center is available all the time. So, it creates planned orders on the same date based on the requirements despite capacity shortages. You can execute those orders on that Work Center in the system which is not practically feasible in the shop floor. The main objective of the capacity leveling includes leveling overloads at Work Center and to achieve optimum utilization of Work Centers. MRP generated planned orders are converted to production orders which determine which Work Center is to be used, and accordingly the capacity requirements are generated on that Work Center. Capacity levelin